Officials approve retention of Broadford Bridge access track

Council officers have allowed the access track to remain to the former Broadford Bridge oil exploration site in West Sussex.

Broadford Bridge access track

The site, near Billingshurst, has been suspended for about eight years. The operator, UK Energy Group plc (formerly UK Oil & Gas plc), is subject to official enforcement action to return the well pad to farmland.

But the track, originally constructed in about 2015, can remain, following a decision this week.

The planning permission was granted to Sheila Francis by county council officers on 21 September 2026 under delegated powers. It did not go to a planning committee meeting of councillors. Link to planning application

The approval allows retention of the 4.5m wide, 400m long track. It also permits the installation of two new 5-bar steel agricultural gates with Adversane Lane.

It requires the applicant to submit a landscaping plan within six months. This is expected to include belts of native shrub planning alongside parts of the track.

According to a report on the application, there were no objections from local councils. Three objections from members of the public focused on:

  • Failure to adhere to previous commitments/planning requirements to restore the land following completion of temporary hydrocarbon exploration activities.
  • No agricultural need demonstrated
  • Impacts on historic landscape character
  • Loss of agricultural land
  • Loss of habitat and potential impacts on biodiversity

The report by planning officer, James Neave, said:

“it is considered that the development would support the needs of agriculture and would likely result in modest operational benefits to agricultural practices”.

The report also said:

“the proposed development would suitably integrate with its countryside setting and not give rise to any unacceptable landscape character or visual impacts.

“It is further considered that agricultural use of the track would be consistent with established farming activities and would not lead to any significant increase in the overall level of activity in the countryside.”

Planning breach

The Broadford Bridge exploration site, at Woodbarn Farm, has had no planning permission since March 2024 when West Sussex County Council refused an application for a fifth extension of consent. Before that, the site had been mothballed since 2018.

An operation to plug and abandon two Broadford Bridge wells ended in February 2026.

But the well pad, fencing, gates and soil bunds remain, despite a planning condition requiring the operator to return the site to farmland. West Sussex County Council took enforcement action in January 2025 and February 2026.

The officer’s report said:

“the main well pad and associated bund and fencing are in the process of being removed/the land resorted [restored] to agriculture.”

It added:

“The site is subject to live enforcement action (Breach of Condition Notices), that require the restoration of the site by the end of 2026.”