Restoration of the Broadford Bridge oil site in West Sussex is due to begin this summer, officials have confirmed.

The site, near Billingshurst, is subject to two council planning enforcement notices after the operator, a subsidiary of UK Oil & Gas plc (UKOG), failed to return the well pad to farmland.
Broadford Bridge has had no planning permission since March 2024 when West Sussex County Council refused an application for a fifth extension of consent. Before that, the site had been mothballed since 2018.
An operation to plug and abandon two Broadford Bridge wells ended in February 2026.
But the well pad, fencing, gates and soil bunds remain, despite a planning condition requiring the operator to return the site to farmland. West Sussex County Council took enforcement action in January 2025 and February 2026.
A council spokesperson said today:
“Two Breach of Condition Notices (BCNs) were served on 13 February 2026. These remain live and require the operator to remove all associated infrastructure (including buildings, plant, machinery, fencing, gates and other structures) and restore the site in accordance with the approved restoration scheme by 31 December 2026.
“The operator has advised that the intention is for restoration works to commence this summer with a view to achieving restoration by the required date.”
Restoration includes work to clean and remove surface stone layers, take-up impermeable membranes, in-fill drainage ditches and regrade the soil from surrounding earth bunds to return the site to its original appearance and use.
Access application

The restoration timeframe emerged in a new planning application for Broadford Bridge (WSCC/036/26).
The application, to keep the site access track, was submitted on behalf of Sheila Francis by the Zetland planning consultancy which has previously worked for UKOG companies.
It revealed: “the well site is to be restored (Summer-Autumn 2026)”.
The application seeks to retain the 450m track to the well site for “agricultural purposes” and the junction of the track with the B2133 Adversane Lane. The application does not seek to retain the former well pad area and fencing around it.
Comments on the access track application can be made online. The deadline for comments is 20 August 2026. A decision is expected by 21 September 2026.